Military Contract in Mirosławiec Completed
In September 2024, the consortium of T4B Budownictwo and T4B successfully completed another military contract, this time in Mirosławiec. The investor was the Regional Infrastructure Authority in Szczecin.
Under the contract signed in July 2020 between the consortium of T4B Budownictwo Sp. z o.o. and T4B Sp. z o.o., and the Regional Infrastructure Authority in Szczecin, we will carry out construction works involving the renovation of the staff building and the construction of a structured cabling network in Koszalin.
Completion date: Second half of 2021
Contract value: approx. PLN 12 million
In September 2024, the consortium of T4B Budownictwo and T4B successfully completed another military contract, this time in Mirosławiec. The investor was the Regional Infrastructure Authority in Szczecin.
T4B Budownictwo has secured a contract for construction works under the project "Reconstruction of the External Perimeter Fence at the Lublin Remand Centre." The agreement was signed on August 14, 2024. The investor is the State Treasury – Lublin Remand Centre.
In July 2024, T4B Budownictwo completed the first stage of the investment project.