Military Contract in Mirosławiec Completed
In September 2024, the consortium of T4B Budownictwo and T4B successfully completed another military contract, this time in Mirosławiec. The investor was the Regional Infrastructure Authority in Szczecin.
In September 2024, the consortium of T4B Budownictwo and T4B successfully completed another military contract, this time in Mirosławiec. The investor was the Regional Infrastructure Authority in Szczecin.
The agreement covered construction and renovation works aimed at adapting the building to the user's needs, including construction works, sanitary installations, electrical, teletechnical, and telecommunication systems.
In September 2024, the consortium of T4B Budownictwo and T4B successfully completed another military contract, this time in Mirosławiec. The investor was the Regional Infrastructure Authority in Szczecin.
T4B Budownictwo has secured a contract for construction works under the project "Reconstruction of the External Perimeter Fence at the Lublin Remand Centre." The agreement was signed on August 14, 2024. The investor is the State Treasury – Lublin Remand Centre.
In July 2024, T4B Budownictwo completed the first stage of the investment project.